- Long-Awaited Air Quality Permit for Tenaska Generating Station Now Available for Public Comment
Westmoreland County residents: The time to weigh in on the long-awaited Title V operating permit for the Tenaska For the uninitiated: Tenaska is a 940-megawatt, natural gas-fired power plant with two large turbines In the meantime, Tenaska continued to operate under its Plan Approval. About Tenaska’s Title V Operating Permit We’re pleased to report that Tenaska and DEP seem to have What Pollution Tenaska Will Be Permitted to Emit Here’s the interesting part: In the years Tenaska
- 4 Years Later, Issues at Tenaska Westmoreland Power Plant Prevent Full Compliance Determination
Today we want to talk about the Tenaska Westmoreland Generating Station, a two-turbine, 940-megawatt, Although Tenaska Westmoreland is a major source of air pollution under the Clean Air Act and has operated So we decided to find out why Tenaska Westmoreland has been permitted to operate subject to temporary Tenaska Westmoreland’s Plan Approval sets emission limits for a host of pollutants including nitrogen A Tenaska investigation into the cause of the failed January 2019 compliance test concluded that the
- GASP Reaches Settlement Agreement with DEP & Tenaska PA Partners re: Westmoreland Generating Station
the Pennsylvania Department of Environmental Protection’s (DEP) issuance of an air quality permit for Tenaska We’re pleased to announce that last month GASP reached an agreement with DEP and Tenaska to resolve the According to Tenaska’s estimates, the station would have the potential to emit 2,310 tons per year (TPY Over the summer, GASP, Tenaska, and DEP discussed the issues we raised in our appeal, and Tenaska and #Tenaska #settlementagreement #WestmorelandGeneratingStation #DEP #airquality
- STATEMENT: GASP Condemns EPA’s Repeal of Power Plant Pollution Standards
Conemaugh, Keystone, and the recently shuttered Homer City, to large natural gas-fired facilities like Tenaska
- GASP Investigates: Title V Operating Permit Backlog Persists Despite Official Denials
The Tenaska Westmoreland Generating Station in Westmoreland County has been constructed and operated DEP published a draft Title V Operating Permit for Tenaska in October 2025, but has not yet issued a
- Watchdog Update | Newest on DEP’s Air Quality Permit Backlog; GASP Report Spurs WTAE Investigation
Two major sources in the Southwest Region –Hill Top Energy Center in Greene County and Tenaska Westmoreland
- Title V Operating Permit Backlogs Exist, Underscores Need for Revisions to Allegheny Co. Health Dept. Fee Schedule
reclassified as a major source but has not yet submitted an application for a Title V Operating Permit; The Tenaska
- INVESTIGATION: ACHD Air Quality Permit Backlog Worst It's Been in Years; DEP Making Progress
Two major sources in the Southwest Region – Hill Top Energy Center in Greene County and Tenaska Westmoreland
- GASP INVESTIGATES: Despite Fee Changes, Air Quality Permit Backlog Still an Issue for ACHD, DEP
Region – CPV Fairview Energy Center in Cambria County, Hill Top Energy Center in Greene County, and Tenaska